شعار وزارة الصناعة والثروة المعدنية
Ministry of Industry and Mineral Resources logo
×

It is a document granted by the Ministry of Industry and Mineral Resources to engage in the industrial activity in all industrial fields as determined by the investor in this document.

  • Enter senaie platform
  • Create a new user account
  • Activate the account via the link sent to your e-mail
  • Apply a new industrial license

The Ministry issues the industrial license for the factory, and it is valid for five years, renewable for a period or similar periods. In case of the license is renewed under an undertaking, the renewal shall be for one year.

No, it’s for free.

It is the Ministry of Industry and Mineral Resources - industrial services agency - industrial licenses management.

It depends on the location of the industrial facility, which is two types:

First: factories inside the industrial cities include (Modon - Economic Cities and Special Zone Authority - Royal Commission for Jubail & Yanbu)

The required documents are as follows:-

  • A valid lease agreement contains the industrial activity.
  • A valid commercial register in the name of the industrial facility contains the industrial activity.

Second: factories outside the industrial cities, which are the industrial zones of the Ministry of Municipal Rural Affairs

The required documents are as follows:-

  • A valid lease agreement contains the industrial activity.
  • A valid commercial register in the name of the industrial facility contains the industrial activity.
  • A municipal license in the name of the industrial facility contains the industrial activity.
  • An environmental permit from the National Center for Environmental Compliance.
  • An approval certificate from the Civil Defense or a safety license from an office accredited by the Civil Defense.

In addition to the documents above, the foreign investor must has an investment license in the name of the industrial facility, the industrial activity, products, the total funding and the number of workers identical to the industrial license.

You can renew it through senaei platform.

You can print it through senaei platform and choose the list of industrial licenses.

  • Obtaining a financial exemption for workers.
  • Obtaining a customs exemption for raw materials and equipment.
  • Employment support service.
  • Chemical releases service.
  • Local factories are a priority for contracting with government and private agencies by using the document as an official document.

The industrial cities, Royal Commission for Jubail and Yanbu and Economic Cities and Special Zone Authority. Also, the industrial regions approved by the Ministry of Municipal Rural Affairs and Housing. It is also possible to issue the industrial license for the industrial activities that have contracts with government agencies, such as ports, universities, Saudi Aramco, etc. For food industry activities in the agricultural scope must be approved by the Ministry of Environment, Water and Agriculture before the approval of the municipality.

Laboratories and workshops do not require industrial licenses to engage in the activity. They are directly supervised by the municipalities and they have commercial registers for these activities. If any of these activities desires to obtain the industrial license, the activity must be modified to an industrial activity in all documents according to the conditions of the Ministry of Industry and Mineral Resources.

The industrial facilities located in the industrial cities, Royal Commission for Jubail and Yanbu, and economic cities that have an industrial activity lease agreement and a valid commercial register of the industrial activity. Then, the request is examined. In case of the request data is completed, it will approved without the need to visit the factory even if the factory is under construction. As for the industrial facilities located in the municipality scope, the factory must be fully completed, and then a field visit to the factory to issue the industrial license.

  • Examining the request by a filed visit to the site, inspecting machines, production lines, and raw materials related to products and necessary evaluating workers to operate the factory.
  • To ensure the legal situation of the industrial facilities according to the requirements of the industrial license.
  • To ensure the products conformity to energy efficiency standards.
  • Following up the technical regulations of Saudi Standards, Metrology and Quality Org.
  • Ensuring compliance with the laws, regulations of safety, industrial security and public health.

The owner of the industrial facility or the authorized person must update the data periodically and quarterly. Completing the industrial survey and (ensuring the update is sent) to avoid the suspension of facility accounts or exclusion from some of the advantages offered by the ministry to the industrial sector. s

Products must be complied with the approved specifications and standards. Also, investors must adhere to those specifications to avoid confiscation and destruction of their products.

After issuing the industrial license, and then visiting the industrial facility to evaluate its need for workers, the request will be approved.

Yes, you can by adding workers to the industrial license according to the list of careers of the license, and then you can apply for employment support.

According to the approval of the National Classification for the Industrial Economic Activities (ISIC 4), the industrial activities will be recorded in the commercial register without the need to mention products. The activities will be approved based on the products added by the investor in the industrial license.

One of the requirements for issuing a new industrial license for (factories located outside the industrial cities) or renewing it for all factories (whether inside or outside the industrial cities in case of renewal). It must have a valid environmental permit in order to comply with the articles of the general environment system and its executive regulation to save the environment from pollution.

You can choose an individual institution if the entity of the industrial facility of the commercial register is an individual institution, and then enter ID of the owner. If the entity of the commercial registry is a company limited liability / mixed, you can choose a company and enter the main commercial registry number and the unified facility number (700) for the main registry, in addition to complete the required data. Registration is not possible for the same facility more than once.

If the registration is correct and the investor has the industrial license issued before creating the platform. In this case, you can contact the ministry and you have to provide proof to be linked via the following e-mail: (industry-licenses.mim.gov.sa) Or you can check at the nearest branch for the necessary work.

Initial approvals (initial industrial licenses) of the Ministry of Industry and Mineral Resources have been cancelled. You can apply for the final industrial license immediately if the required conditions met. You can also submit the commercial register that includes the industrial activity to the relevant government agencies to obtain the necessary licenses to issue the industrial license.

The required name is the commercial name of the facility in the commercial register of the factory and it must be matched to the name without any difference.

The industrial investment license issued by the Ministry of Investment is a basic reference for the issuance of the industrial license. As it depends on the facility name recorded in the investment license in the industrial license as well as in the commercial register. As for products, production capacity, number of workers and the total financing must matched to what is mentioned in the investment license. In the event of a desire to increase the above-mentioned data, you have to modify it the investment license because it is the main reference.

The location must be inside or outside the cities. Inside the cities include the Saudi Authority for Industrial Cities and Technology Zones, Economic Cities and Zones Authority and Royal Commission for Jubail and Yanbu, and everything else is outside the industrial cities.

  • Land area / is the total land area stated in the lease agreement
  • Buildings area / is the area of the facility building includes production, administration and warehouses areas.

Data of the facilities means electricity, fuel, water and their quantities, which are annual estimates with a minimum and maximum limit for the quantity, also a price of each facility separately, as shown in the table below:

(quantity)Electricity watt10.000.000 -200.000
(per kWh)Electricity SAR 0.18
(quantity)Fuel (liter - gallon - ton) 100.000not exceed
(price ton) Fuel SAR 1.000 300
(quantity)Water (gallon - ton) 1.000.000- 200
(price ton) Water SAR 10 6

platform system only allows you to add the product manually, and the industrial activity associated with the product appears automatically based on the product you have added.

You can attach documents through an icon at the bottom of the product data page. You can attach documents in PDF format with a maximum of five attachments only.

You can merge more than one document into one PDF file so that the total of the files is only five. For example, the municipal license can be merges with a letter of undertaking in one file.

The total financing and the rate of return for investment are values that appear automatically based on the data entered and include data of the industrial facility, data of products, raw materials, machines and wages of the workforce.

The rate of return for investment must be positive value at least 8% and not more than 35%. If the rate value appears negative, you can review the price and value of the sales unit of products and raw materials so that the products prices are raised, and reducing the raw materials value. Thus, increasing the rate of return for investment and doing the opposite for reducing it if desired.

There are some items or customs codes for materials and machines that have been updated by the customs authority. Therefore, old codes have become ineffective. To update them, you can click on the modification icon, and then choose the correct code by searching by the name of the machine / material or by searching with the first four numbers of the old code, thus codes are updated.

It is determined based on the amount of funding as follows:-

The initial stage, with an emphasis on the investors that this evaluation is not the final and can be modified according to the project stages progress.

Class A Small projects with a total financing must not exceed 2 million The number of workers 15-20
Class B Medium-sized projects with a total financing of 2-10 million The number of workers 20-30
Class C Projects with a total financing more than 10 million The number of workers 30-50

The actual size of workers is evaluated through a field visit. Also, checking the production area, the actual production capacity and the number of production lines.

Categories must be added according to the standardized classification of jobs approved by the Ministry of Human Resources. All actual jobs of the industrial facility must be added so that the titles of administrative jobs, in addition to the titles of technical jobs are added according to the operational need of the industrial facility.

Applying for (license modification) through senaei platform and attaching a letter in the same request indicating the type of modification made in the request. In some cases of modification, such as increasing the amount of financing, or increasing products must be matched to the investment license for modification and the approval of the industrial development fund in case of a loan or non-borrowing certificate.

You can contact the National Industrial Mining Information Center, and then make a request to add products, machines or raw materials after checking names and codes by the customs tariff department of Saudi Customs via the following email: (niic@mim.gov.sa)

In case of the factory is moved to another location, apply for modification license request. The new location of the factory is specified in the map in the request so that the location coordinates are accurately specified to facilitate access to the factory in case of the ministry visiting. Also, a letter must be attached of the new location address, in addition to the documents of the new location, such as the lease agreement, municipality license and commercial registry.

One of the requirements for transferring the ownership is the new owner creates a user account for the new owner on senaei platform with the owner’s ID if the entity is an individual institution. If the legal entity of the industrial facility (a company limited liability / mixed) enter the main commercial registration number. Then, apply for transferring the ownership from the account of the new owner on senaei platform not from the account of the previous owner.

Apply for license modification through senaei platform. Then, the name of the industrial facility will be changed and attach a copy of the new commercial register.

The supervising authority of the industrial activity of some special activities, for example if the factory produces food, the supervising authority is Saudi Food & Drug Authority. Another example, a factory produces military clothing must obtain the approval from the Ministry of Interior. As for a printing factory (a printer shop) must obtain a license from the Ministry of Media.

The status The meaning of the status (notes)
A draft The investor created the request, but it was not completed and sent into the system. Thus, (the ministry cannot access to the request content).
New The first stage of data review, which means that the investor sent the request, but it was not viewed by the competent employee
Under evaluation The second stage of data review, which means that the employee has viewed the request to examine and evaluate it
Need to modify A reiterated request to the investor for modification - and it has been reiterated from the first stage as new
Reiterated The investor modifies notes and resends the request again in the system
Pending the examination The request was included in the visits schedule and a field supervisor will contact the investor during a working week
Under the examination It means that the competent employee withdrew the request and work is underway for the field visit to the industrial facility
Under the approval The resident approved the request. It is awaiting the approval of the licensing manager, and it will be during one working day
Approved The manager approved the request. It is in the process of printing, signing and exporting during one working day

Because of a draft request, modification request that has not been completed, or the validity period of the license is more than six months. In this case, the pending requests must be deleted to appear the renewal icon. If the icon does not appear after deleting the requests, you can contact technical support via the following email: (ihd@mim.gov.sa)

There are many reasons which are as follows:-

  • The financial exemption does not cover the expiry of the work permit for more than one year (it will be charged for the past and current year).
  • The number of Saudi and foreign workers exceeded the number licensed in the industrial license.
  • The facility scope is not high green or platinum.
  • The expiry date of the industrial license.
  • No industrial survey each calendar quarter.
  • The industrial license is not upgrading on senaei platform system.
  • The factory facility stops working and the factory’s status on the platform is changed to stopped, and then the exemption will be suspend. It is not possible to modify the license in this case.
  • The industrial activity is not adding in the file (in the commercial register) of the factory of the Ministry of Human Resources.
  • For inquires about the status of the financial exemption, you can contact the investor support department via the following e-mail: (isa@mim.gov.sa)

You must prepare a certified letter from the Chamber of Commerce to recover the username and password, and attach the main commercial register if it is a company or ID if it is an individual institution. Then, send it to the following e-mail: (isa@mim.gov.sa)

In case of the facility actually started production, you can check at the nearest branch of the ministry to schedule a visit to the factory to ensure the start of production and to modify the status to a product, or send a certified letter from the Chamber of Commerce that includes the date of the start of production and asks to change the factory’s status under construction to a product. Then send it to the following email: (industrial.licenses@mim.gov.sa)

You can obtain the certificate through the industrial license status inquiry service at the following link (link)

You must first apply to cancel the industrial license on senaei platform system, and then you can obtain a certificate stating that there is no industrial license of the commercial register to be canceled.

  • Variable assets are the company's expenses that change according to the production output. Also, they mean costs that change according to the amount of the production company; it can be raised according to the production increase, and decreases according to the decrease in production. Examples of variable assets (costs of raw materials, packaging, wrapping, the service expenses and any other costs of its characteristics change according to the volume of sale or production.
  • As for costs or fixed assets are expenses that remain fixed regardless of the amount of production, whether the company makes sales or not, it must pay its fixed costs. Examples of fixed costs include rent, salaries for administrative staff, insurance, and office supplies. The company must be committed to paying the area rent for its business, regardless of the volume of production.

Consumptions are the result of the following calculation: The value of fixed assets * 15% and the result is the value of consumptions.

You can apply for the industrial license cancellation on senaei platform.

At the present stage, there is no English version, but the license can be translated at one of the accredited translation offices.

In this case, you can go to the Ministry of Industry and Mineral Resources in Riyadh to document and to approve the translated license.

It is granted by the government to factories that have the industrial license under the Common Industrial Regulatory Law (Regulation) of GCC for exempting them from tax (customs duties) on their imports of machines, equipment, spare parts, raw materials, semi-finished and finished materials, and necessary packaging and wrapping materials directly for production throughout the period of the industrial facility.

  • The factory has a valid industrial license.
  • The factory has a valid commercial register that matches the name of the facility of the industrial license.
  • The imported item has not a local similar item in the local factories.
  • Machines and spare parts have to be of the factory supplies.
  • The quantity of the required materials shall not exceed the licensed production capacity of the factory.

You can apply for the exemption through senaei platform of the Ministry of Industry and Mineral Resources by logging into in the investor’s account on the platform, and then you find all the services provided by the industrial services agency. One of those services is customs exemption, and then you find three icons, which you can choose any of them according to what you wish as follows:

  • A basic exemption of materials request.
  • An append exemption of materials request (this icon works in case you have a valid basic exemption of materials request).
  • Machines or spare parts request.

The factory can also apply for exemption of materials, machines or spare parts at the same time in the section dedicated to it.

  • When choosing the type of exemption request (basic, append, machines or spare parts), click on start icon, then a page appears through which you can choose the exemption period.
  • Move to the next page that includes the field to add items to be imported by entering (HS Code) for the required item (materials, machines and equipment will appear only (HS Code) added to the industrial license form).
  • Write the name of the item and it must be matched to the name in a purchase invoice in the item description (English) and translate it in the item description field (Arabic).
  • Write a brief of the required item in the additional justifications (optional) if necessary
  • Specify the required quantity not exceed the licensed materials, machines and equipment in the industrial license form.
  • Move to the attachments field. The factory must attach a copy of the factory's commercial register and letters of apology from the local factories for available items locally. Also, attach the manufacturing value-added form or any document that helps to clarify in detail, such as pictures, invoices, catalogs, technical publications, and manufacturing methods if this is requested by the resident.
  • Click on send icon.

It is the start period of the exemption decision implementation for customs.

It is divided into two main types:

  • Exemption of raw materials (includes raw materials, semi-manufactured and finished materials, packaging and wrapping materials necessary and directly for production).
  • Exemption of machines, equipment or spare parts.

  • It is divided into:

    Basic materials request: the investor can apply for the exemption for all his needs of necessary licensed raw materials and directly for production for one year and unavailable locally. If the request is accepted and the exemption decision is issued for the factory, thus the decision is issued for one year and renewed for four years. The decision is renewed annually and automatically for the remaining four years by Saudi Customs.

  • To reconsider the basic request:

    The investor can reapply for the rejected items in the basic request within 60 days from the date of issuance of the decision for the basic request.

  • An appendage exemption request:

    The investor can apply for an appendage exemption of the appendage materials to increase the exempted quantities in the basic decision or new items that were not applied in the basic application (increasing) not exceed the required quantity for the licensed production capacity of the factory (taking into account it will be charged for what was exempted in the basic decision). If the request is accepted and the appendage exemption decision is ​​issued, the exemption period is automatically determined through the online system for exemption. The exemption period begins from the renewed year of the basic exemption (the subsequent renewal year will be from the year of the request).

  • To reconsider the appendage request:

    The investor can reapply the rejected items in the appendage request within 60 days from the date of the decision issued for the appendage request.

The investor can apply for the exemption of machines or spare parts for all his needs in one request. If the request is accepted and the decision is issued, the validity of the decision will expire after 3 years or the expiry of the exempted quantity, whichever comes first. Note that the factory cannot obtain more than 4 decisions during one calendar year.

The factory can apply for the exemption at an earlier or a later date. The invoice date does not exceed a full year from the date of the exemption request. It must not have a valid materials exemption request.

There is a similar item to the imported one at the local factories, and the investor must provide it from those factories. If it is unavailable, the factory can contact those factories with the name of the item and its specifications. If it is unavailable, the local factory will reply to the investor’s letter that it is unavailable. Then, the investor attaches the letter when applying for the exemption through the platform.

You can check at the National Industrial Mining Information Center and give them the customs item number of the imported item. Then, they provide you with a list of local factories that produce the item locally and available.

Yes, you can after examining the request and the possibility of modification by submitting a modification request letter directed to the Department of Industrial Exemptions.

Click on a chemical release service and choose the customs item of the material from the list of raw materials of the industrial facility. Then, enter the chemical abstract number of the chemical and the required quantity, after that attach the technical safety publication of the material and send the request.

There are requirements for any chemical release service and lists of chemicals shown on the login page.

It is a service to request an import permit for the security-restricted chemicals in the first, second and third lists, as provided in the executive regulations of the chemicals management system. You can find the lists on the login page.

You can check at the Ministry of Interior with the request number to issue the import permit and the release permit, because it is the competent authority, as provided in the executive regulations of the chemicals management system.

Yes, you can choose more than one customs port. In case of it is not added to the request and you wish to add it later, you can send the additional request to the administration’s e-mail: (chd@mim.gov.sa)

Yes, you can on condition that the trade name of the material is different.

No you cannot. A release request can only be applied for chemicals added to the facility's account on senaei platform as raw materials.

Choose the correct customs item through Saudi customs website or by an approved customs broker from Saudi customs, and the validity of the customs item is the responsibility of the facility. You can log into your account on senaei platform and modify the license, and then modify the customs item in raw materials. After the approval of the licensing department, you log in and choose the chemical release to apply for the release of the correct customs item.

It must be related to the required material and has a fee category on Saudi customs website.

Click on the customs shipments icon in your account and choose view request, and you find the customs reference number at the bottom of the page. You can provide the customs broker with the number to print the customs declaration and enter your shipment.

It takes 1-2 working days if all requirements are completed.

One calendar year from the date of approval.

You can apply before the end of the current release for at least five working days.

Log into your account on senaei platform and modify the license, and then modify the quantity of the customs item of raw materials and send the request. After the approval of the licensing department, you can choose the chemical release to apply for release for the added quantity.